30 farmer could reap a crop in 20 days,but after 5 days 5 farmers didnot turn up.How many more days will the rest require to reap the same crop?
by
retagged by

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:
To avoid this verification in future, please log in or register.

1 Answer

total work to be done= 30 x 20 farmerdays = 600 farmerdays

work done in first 5 days = 30 x 5 = 150 farmer days

Remaining work(600-150) to be done within ? days by 15 farmers = 450/25 = 18 days
by
correct.....................................
yeah absolutely right..........

Related questions

0 answers
asked Feb 27, 2014 by Dileep yadhuvanshi
0 answers
0 answers

Welcome to Tech Support Questions, where you can ask questions and receive answers from other members of the community.

Post questions regarding any technology problem including problems with phones and tablets, computers and laptops, windows and apple devices and more. Help other members of the community by answering questions.

Note: Please do not post private information such as passwords or usernames.

5,769 questions
2,928 answers
141 comments
31,545 users