30 farmer reap a crop in 20 days,but after 5 days 5 farmers left.Days will the rest require same crop?

30 farmer could reap a crop in 20 days,but after 5 days 5 farmers didnot turn up.How many more days will the rest require to reap the same crop?
asked Nov 20, 2013 by anonymous
retagged Aug 1, 2015 by mshelton

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:

To avoid this verification in future, please log in or register.

1 Answer

total work to be done= 30 x 20 farmerdays = 600 farmerdays

work done in first 5 days = 30 x 5 = 150 farmer days

Remaining work(600-150) to be done within ? days by 15 farmers = 450/25 = 18 days
answered Nov 20, 2013 by Hardik Mandalia
correct.....................................
yeah absolutely right..........

Related questions

0 answers
asked Feb 27, 2014 by Dileep yadhuvanshi
0 answers
asked Nov 18, 2013 by sadia malik
0 answers
asked Jun 29, 2014 by yeshua (120 points)
...